Transmission at the Breaking Point: Why the Grid Is Becoming the Defining Constraint for AI Data Centers

AI data center growth is driving unprecedented electricity demand, exposing U.S. grid and transmission constraints. The 2025 ACEG report highlights regional disparities in transmission planning, warning that grid upgrades are lagging behind AI-driven load growth and threatening future data center expansion and reliability.
Feb. 4, 2026
11 min read

Key Highlights

  • Data centers are now a structural load driver, with load growth expected to surge over sixfold by 2025, primarily due to AI and advanced manufacturing demands.
  • Transmission infrastructure, especially high-voltage lines, is critical for unlocking regional generation resources and supporting large-scale data center development.
  • Regional planning varies significantly, with California leading in long-term strategies, while regions like Texas and the Southeast face higher risks due to fragmented or outdated transmission systems.
  • Interregional transmission is underdeveloped, limiting resilience during extreme weather events and increasing vulnerability to outages and price spikes.
  • The report underscores the urgency for grid reform, including faster adoption of federal policies like FERC Order No. 1920, to meet the rapid pace of AI-driven load growth.

The U.S. data center industry is no longer a niche contributor to electricity demand. It has become a central force reshaping the nation’s power system, with accelerating data center load growth now exposing the limits of the national grid.

That reality is underscored in the 2025 Transmission Planning and Development Report Card, published by Americans for a Clean Energy Grid (ACEG). The report assesses how effectively U.S. regions are preparing their high-voltage transmission networks for a future defined by accelerating load growth, extreme weather, and electrification. Data centers sit squarely at the center of that challenge. The judgments and grades referenced here reflect ACEG’s findings, not those of this publication.

While the report identifies incremental progress in transmission planning nationwide, its broader conclusion carries a warning for hyperscalers and colocation providers alike: grid reform is not keeping pace with AI-driven demand growth. In many regions, transmission planning remains reactive, fragmented, or too narrowly scoped; conditions that threaten to make the grid itself the next major bottleneck for data center expansion.

Data Centers as a Structural Load Driver

Perhaps the most consequential shift captured in the report is the reframing of electricity demand growth. What was once treated as cyclical or speculative is now seen as structural; with data centers, particularly the rapid expansion of AI-focused facilities and AI factories, emerging as a primary driver.

According to forecasts cited in the report, nationwide five-year peak load growth expectations have surged more than sixfold in just three years, rising from roughly 24 gigawatts in 2022 to approximately 150 gigawatts by 2025. Grid analysts identify data centers and advanced manufacturing as the dominant contributors to this increase.

This trajectory carries major implications for transmission planning. Unlike traditional incremental load additions, hyperscale and AI-centric data centers often arrive in clusters, with individual campuses demanding hundreds of megawatts of firm, around-the-clock power. The result is intense, geographically concentrated pressure on transmission systems that were largely designed for slower, more diffuse growth.

The report warns that this environment can push planners and utilities into a crisis-response mindset, prioritizing short-term fixes to achieve speed to power while deferring more comprehensive, long-term solutions. ACEG argues that this approach ultimately sacrifices economies of scale and raises both system costs and reliability risks for all customers.

Why Transmission, Not Generation, Is the Constraint

For years, data center power discussions focused primarily on generation: natural gas availability, renewable procurement, nuclear prospects, and on-site backup capacity. The ACEG report underscores that in many regions, generation is no longer the limiting factor. Transmission is.

High-voltage transmission lines unlock access to diverse generation resources, enable regional load balancing, and can significantly reduce system costs when planned at scale. The report notes that a single 765-kilovolt line can deliver six to ten times as much power as a 230-kV line while requiring only a fraction of the right-of-way and offering a much lower cost per unit of energy delivered.

For data centers, this distinction is critical. Large campuses can secure interconnection agreements yet still face years of congestion, curtailment risk, or costly network upgrades if regional transmission infrastructure has not been built proactively. In other words, interconnection does not guarantee deliverability.

Regional Winners and Losers in the AI Era

The report evaluates ten U.S. regions across four dimensions: regional transmission planning, interregional coordination, stakeholder engagement, and planning outcomes. The resulting scorecard highlights stark differences in how prepared regions are to accommodate the next wave of large-scale data center development.

Regions in a Position to Scale

California (A- overall)
California continues to lead in long-term, scenario-based transmission planning. CAISO’s most recent transmission plan identifies $4.8 billion in new projects to accommodate approximately 76 gigawatts of additional capacity by 2039, explicitly accounting for data center growth alongside broader electrification.

For data center developers, California’s challenge is less about planning quality and more about execution. Permitting timelines, cost allocation debates, and political scrutiny remain significant hurdles.

Plains / Southwest Power Pool (B- overall, A in regional planning)
SPP stands out nationally for embracing ultra-high-voltage transmission as a backbone strategy. Its recent Integrated Transmission Plans approve more than $16 billion in new projects, including multiple 765-kV lines, with benefit-cost ratios exceeding 10:1.

This approach positions the Plains region as one of the most structurally “AI-ready” grids in North America, particularly for multi-gigawatt campuses supported by wind, natural gas, and emerging nuclear resources.

Midwest / MISO (B overall)
MISO’s Long-Range Transmission Planning framework aligns closely with federal best practices, co-optimizing generation and transmission over long planning horizons. While challenges remain—particularly around interregional coordination—the Midwest is comparatively well positioned for sustained data center growth.

Regions Facing Heightened Risk

Texas / ERCOT (D- overall)
Texas has approved massive new transmission investments, including 765-kV projects tied to explosive load growth in the Permian Basin. However, the report criticizes ERCOT’s planning for remaining largely siloed and reliability-driven, with limited long-term scenario analysis and narrow benefit assessments.

For data centers, ERCOT still offers speed to market, but increasingly with risks tied to congestion, price volatility, and political backlash surrounding grid reliability.

Southeast (F overall)
The Southeast receives failing grades across all categories, with transmission development remaining fragmented, utility-driven, and largely disconnected from durable regional planning frameworks.

As AI data centers increasingly target the region for its land availability and tax incentives, the lack of coordinated transmission planning raises the likelihood of future bottlenecks, rate shocks, and community opposition.

Interregional Transmission: The Missing Link for Resilience

If regional planning gaps are concerning, the report finds even greater shortcomings in interregional transmission. Despite extensive research showing that interregional lines can deliver roughly $5 in benefits for every dollar invested, most U.S. regions plan little interregional transmission. Where coordination exists, it is often voluntary, limited to reliability studies, and constrained by misaligned assumptions and cost-allocation disputes.

For data centers, this weakness directly affects resilience. Interregional transmission functions as an insurance policy during extreme weather events, enabling regions under stress to import power from neighbors with surplus capacity. Without it, large loads face greater exposure to price spikes, curtailments, and outages.

The report highlights voluntary efforts such as the Western Transmission Expansion Coalition (WestTEC) as promising models, but notes that such initiatives lack the durability and authority required to meet future demand at scale. Voluntary coordination alone is unlikely to be sufficient going forward.

FERC Order No. 1920: Reform Arrives. But Is It Arriving Too Slowly?

Federal Energy Regulatory Commission Order No. 1920 is a central pillar of the report. The rule requires regions to adopt 20-year planning horizons, scenario-based modeling, multi-value benefit analysis, and improved cost-allocation frameworks.

Yet every region in the country has received extensions on compliance deadlines, and in many cases projects planned under the new framework may not receive approval until well into the 2030s.

For the data center industry, the mismatch is stark: AI infrastructure investment cycles operate on years, not decades. As a result, developers are increasingly moving upstream: co-funding transmission, partnering directly with utilities, or selecting sites based on grid readiness rather than traditional metrics such as fiber proximity or tax incentives.

What This Means for Data Center Strategy

The ACEG report makes one conclusion unavoidable: transmission planning quality is becoming a decisive factor in where AI data centers can scale.

Several strategic implications follow:

  • Transmission is now a core site-selection variable, not a secondary consideration.

  • Regions building high-voltage backbone systems are structurally advantaged for AI growth.

  • Interconnection agreements alone are insufficient without long-term deliverability planning.

  • Hyperscalers will increasingly act as grid stakeholders, not just customers.

  • And while not explicitly covered in the report, co-generation, on-site power generation, and other behind-the-meter strategies are becoming increasingly important components of data center development planning.

The Grid as the Next Bottleneck

The 2025 Transmission Planning and Development Report Card is neither a story of failure nor a victory lap. Progress is visible, and best practices are spreading, but the scale and speed of AI-driven load growth are testing the grid faster than institutions are adapting.

For the data center industry, the message is unavoidable: the next constraint on AI may not be chips, land, capital, or even power availability. It may be transmission. Where the grid evolves quickly enough, AI infrastructure will scale. Where it does not, even the most ambitious digital infrastructure plans may stall.

 

At Data Center Frontier, we talk the industry talk and walk the industry walk. In that spirit, DCF Staff members may occasionally use AI tools to assist with content. Elements of this article were created with help from OpenAI's GPT5.

 
Keep pace with the fast-moving world of data centers and cloud computing by connecting with Data Center Frontier on LinkedIn, following us on X/Twitter and Facebook, as well as on BlueSky, and signing up for our weekly newsletters using the form below.
Contributors:

About the Author

David Chernicoff

David Chernicoff

David Chernicoff is an experienced technologist and editorial content creator with the ability to see the connections between technology and business while figuring out how to get the most from both and to explain the needs of business to IT and IT to business.
Sign up for our eNewsletters
Get the latest news and updates
Leviton Network Solutions
Source: Leviton Network Solutions
Sponsored
Mike Connaughton, Senior Product Manager at Leviton Network Solutions, explains the importance of cabling when transitioning to an immersion cooling system.
Image courtesy of Colocation America
Source: Image courtesy of Colocation America
Sponsored
Samantha Walters of Colocation America shares her thoughts on four trends she's seeing in the colocation space.