Maryland Reboots Data Center Business with New Critical Infrastructure Streamlining Act

May 14, 2024
State government addresses a sticking point on backup power generation that precluded Aligned Data Centers' 264 MW project just seven months ago.

Taking a significant step towards attracting data center development to the state, Maryland's Governor Wes Moore last week signed the Critical Infrastructure Streamlining Act of 2024, which clarifies the definition and legislative framework around the use of emergency backup power generation in the state. 

The law redefines what types of businesses are required to acquire a Certificate of Public Convenience from state authorities in order to install backup power generation systems. 

The Carrot and the Stick

Back in October 2023, the Maryland Public Service Commission (PSC) denied Aligned Data centers application for 160 diesel generators, the number they felt was necessary to provide backup power for Aligned’s planned 264-megawatt (MW) data center campus.

The PSC also rejected Aligned’s application for an exemption of the state’s 2022 emission rules, and determined that only 70 MW of backup power generation would be permitted. 

Despite Aligned’s arguments that they were not defining a power generation station properly relative to data center backup power, the PSC declined to make any changes to their decision. 

This was despite the fact that the original regulation was designed to address commercial power plants and transmission lines, and did not specifically address backup power generation.

The lack of flexibility exhibited by the PSC led to Aligned pulling their project, along with its potential $40 million in annual tax revenue and thousands of potential jobs.

Quick Turnabout re: 'Generating Stations'

The scale of the project being canceled, and the resulting media coverage and lobbying by various groups, led to Maryland looking at redefining “generating stations" in relation to certain industries.

The redefinition came via the new Critical Infrastructure Streamlining Act, which explicitly excludes backup power generation facilities from the auspices of the PSC in these cases.

In a turnabout for tradionally glacially slow government regulation changes, in January of this year, the new bill was introduced and signed into law only seven months from the point the motivating incident occurred.

As laid out by the new statute, Maryland's law now specifies:

While the new law directly addresses the concerns of the data center industry, it also has a positive benefit for other industries that require significant on-site backup power generation, such as hospitals and the telco sector.

A Quantum Shift

The Critical Infrastructure Streamlining Act, signed by Governor Wes Moore on May 9, 2024, passed with a unanimous vote of both the Maryland House and Senate.

Quantum Loophole, who announced the signing of the legislation in a press release on May 13th, is currently developing their first Maryland project, Quantum Frederick, a 2,100-acre development in Frederick County, Maryland that provides land, water, power, and fiber to data centers. 

Quantum Loophole will be a significant beneficiary of the advantages in backup power generation that the new law codifies for the data center industry in the state. The statute goes into effect on July 1, 2024.

As reckoned by Quantum Loophole, "The newly enacted legislation reiterates the state’s commitment to welcoming data centers, and fosters continuous innovation for businesses throughout Maryland."

During Governor Moore’s May 9 press conference where he signed the Act into law, he remarked, “This bill is going to supercharge the data center industry in Maryland, so we can unleash more economic potential and create more good paying union jobs.”

Fast Track for Quantum Frederick

Quantum Frederick's over 2100 acres of entitled, shovel-ready land for deployment of large-scale Internet infrastructure is served by transmission power from First Energy and their wholly owned distribution entity Potomac Edison at multi-gigawatt scale. 

Meanwhile, the largest capacity fiber ring ever constructed, at a capacity of up to 235,000 strands, interconnects the campus to Northern Virginia via underground ducts, designed to exceed the highest security standards as they cross beneath the Potomac River.

Highlighting the Quantum Frederick campus's nearness to the country’s center of data center development in northern Virginia, Rich Paul-Hus, SVP of Public Affairs for Quantum Loophole, commented:

The Quantum Loophole press release doubles down on the value of encouraging data center growth, with the company's Founder and CEO, Josh Snowhorn, telling us:

Buddy Rizer, Executive Director for Economic Development in Loudoun County, Virginia (and as the godfather of Ashburn's famed Data Center Alley, himself no stranger to the plusses and minuses of significant data center development), said: 

Bellwether for Future Data Center Development

It seems important to note how Maryland’s major step to encourage data center development in the state required the government to balance both economic and environmental issues in making their decision.

This required not taking any facet of the development at face value -- and required understanding how backup power is used, when compared to primary generation.

The move also adds another high-level consideration for data center developers, to whom power availability has become a major issue (to say the least).

The Maryland resolution also highlights how issues such as microgrid development and on-site for generation or both primary and backup power have become leading issues in data center site selection and development.

 

Washington, D.C. local news station WUSA9 reports on the signing of Maryland's Critical Infrastructure Streamlining Act of 2024.

 

Keep pace with the fast-moving world of data centers and cloud computing by connecting with Data Center Frontier on LinkedIn, following us on X/Twitter and Facebook, and signing up for our weekly newsletters using the form below.

About the Author

David Chernicoff

David Chernicoff is an experienced technologist and editorial content creator with the ability to see the connections between technology and business while figuring out how to get the most from both and to explain the needs of business to IT and IT to business.

Sponsored Recommendations

Get Utility Project Solutions

Lightweight, durable fiberglass conduit provides engineering benefits, performance and drives savings for successful utility project outcomes.

Guide to Environmental Sustainability Metrics for Data Centers

Unlock the power of Environmental, Social, and Governance (ESG) reporting in the data center industry with our comprehensive guide, proposing 28 key metrics across five categories...

The AI Disruption: Challenges and Guidance for Data Center Design

From large training clusters to small edge inference servers, AI is becoming a larger percentage of data center workloads. Learn more.

A better approach to boost data center capacity – Supply capacity agreements

Explore a transformative approach to data center capacity planning with insights on supply capacity agreements, addressing the impact of COVID-19, the AI race, and the evolving...

Photon photo/Shutterstock.com

In the Age of Data Centers, Our Connected Future Still Needs Edge Computing

David Wood, Senior Product Manager – Edge Computing at nVent, explains why edge computing will play a pivotal role in shaping the future of technology.

White Papers

Dcf Cadence No Capacity Wp Cover 2023 01 11 17 29 43

No Capacity for Change

Jan. 11, 2023
The pace of digital transformation is accelerating bringing not only opportunities, but challenges for technical professionals and digital strategists. Notably, organizations ...