How to Avoid Site Congestion During Data Center Construction

Dec. 7, 2020
Although 2020 is winding down, there’s no slowdown in sight for the data center market.  Growth projections for at least the next couple years are staggering. Blake Weaver, Data Center Specialist  from ProLift Rigging walks readers through five different strategies to avoid congestion challenges during the data center construction process. 

Blake Weaver, Data Center Specialist  from ProLift Rigging walks readers through five different strategies to avoid congestion challenges during the data center construction process. 

Blake Weaver, Data Center Specialist, ProLift Rigging

Although 2020 is winding down, there’s no slowdown in sight for the data center market.  Growth projections for at least the next couple years are staggering.  In a November 2020 CAPRE presentation, Sean Brady with Cushman & Wakefield reported that, “The largest cloud services providers have used all their previously taken capacity from 2018 and require more.”  He further noted that, “Global colocation supply is expected to increase from 13.1 GW to 17.6 GW by 2024.  For context, this would be the equivalent of three new Northern Virginias (the largest global market) in the coming four years.”  This type of growth will equate to a substantial amount of new infrastructure.  Speed to market remains king, and construction contractors must be poised to support with improved efficiency.

Large scale data center construction sites are quite complex.  Multiple trades work simultaneously, a steady flow of equipment deliveries occur, a lot of heavy machinery is in constant motion, key construction schedules often collide, etc.  The combination of these dynamics usually results in site congestion. Although data center construction projects typically include staging areas for crews and equipment, the sites get congested quickly.  It’s almost unavoidable…almost.

Site congestion poses several threats to key construction milestones.  It bogs down the construction process, causes unnecessary safety risks (i.e. heightened risk of COVID-19 exposure), increases on-site staff hours, and fogs communication and planning among contractors. Project success includes completed milestones in expected timeframes, so it’s imperative to deal with site congestion before it occurs.

The typical data center construction site is large; however, workspace is usually limited, and conditions can be hectic.

Fortunately, there are at least a few practical ways to avoid site congestion.  Below are five proven methods:

  1. Just-in-Time (JIT) Equipment Deliveries: Ideally, OFCI equipment is delivered directly to the contractor/installer at the time of need.  This is the best-case scenario.  For instance, a generator, power center, cooling unit, etc. would be delivered directly to the crane hook (bypassing the designated staging area) to be lifted and set at precisely the right time in the construction process.  While this method sounds simplistic, it requires intense coordination among key stakeholders. An October 2018 blog post by NEHP, Inc. states, “The JIT method also requires that suppliers and contractors collaborate at a higher level than in regular construction methods and it requires that all project supplies are up to standard. This helps to prevent project delays…”
  2. Synchronizing Schedules: As the demand for data centers rapidly increases, OEMs face a production challenge of shorter lead times. Moreover, OEMs must align production schedules with construction timelines.  This presents a logistical puzzle that often involves the owner, manufacturer, trucking company, 3PL, contractor, rigging company, etc.  Congestion and delays are reduced when these schedules are adequately synced.  This is no small feat.
  3. Buffering with Off-Site Storage: Nearly every construction project experiences unforeseen equipment production and transportation hiccupsThis strains the original planned construction timelines, and it can be difficult to accommodate unplanned equipment deliveries on site.  An off-site temporary warehouse acts as a pressure relief valve.  Equipment can be delivered to the warehouse, then it can be fed to site as needed for offload and installment.
  4. Utilization of Specialized Equipment On-site: The typical data center construction site is large; however, workspace is usually limited, and conditions can be hectic.  Therefore, it’s tricky to maneuver heavier equipment and gear around the site.  Utilizing specialized equipment to navigate tight spaces and tough conditions helps improve install efficiency and reduce further congestion.  One example is a self-propelled transporter (trailer), such as the PowerHoss.  Its high load capacity and compact maneuverability helps shuttle mission critical equipment around site with ease and precision.
  5. Coordinated Logistics Management: In a May 2017 online article, Bill Brisse stated, “Unfortunately, if logistics are considered at all for a construction site, it is usually as an afterthought.  The absence of a logistics plan for a construction site can lead to the creation of bottlenecks that place a stranglehold on the project”.  Therefore, a good logistics plan developed on the front end will help avoid congestion.  That said, the plan alone is not enough. Someone must tightly manage the overall logistics plan throughout the construction process to ensure and protect predictable outcomes.

Over the past decade, ProLift Rigging Co. has worked closely with countless data center owners, contractors, and manufacturers to avoid site congestion and accelerate critical construction timelines.  The key has been the combination of some or all the methods above, which ProLift refers to as Project Buffering. This has led to deep strategic partnerships that include high levels of trust, visibility, collaboration, and value.  If the data center market growth projections hold true, these types of partnerships will be critical in the quest to expand the cloud.

Blake Weaver is a Data Center Specialist at ProLift Rigging. 

About the Author

Voices of the Industry

Our Voice of the Industry feature showcases guest articles on thought leadership from sponsors of Data Center Frontier. For more information, see our Voices of the Industry description and guidelines.

Sponsored Recommendations

How Deep Does Electrical Conduit Need to Be Buried?

In industrial and commercial settings conduit burial depth can impact system performance, maintenance requirements, and overall project costs.

Understanding Fiberglass Conduit: A Comprehensive Guide

RTRC (Reinforced Thermosetting Resin Conduit) is an electrical conduit material commonly used by industrial engineers and contractors.

NECA Manual of Labor Rates Chart

See how Champion Fiberglass compares to PVC, GRC and PVC-coated steel in installation.

Electrical Conduit Cost Savings: A Must-Have Guide for Engineers & Contractors

To help identify cost savings that don’t cut corners on quality, Champion Fiberglass developed a free resource for engineers and contractors.

kubais/Shutterstock.com
Source: kubais/Shutterstock.com

Exploring the Benefits of Liquid-to-Air Coolant Distribution Units (CDUs)

Kevin Roof, Senior Product Manager at nVent, outlines how liquid-to-air cooling works, its benefits and what data center operators should look for when designing and selecting...

White Papers

DCF_CologixWPCover_2022-10-28_9-28-14

Cologix Access Marketplace – an Open Exchange Built for Business

Oct. 28, 2022
To ensure the speed and flexibility demanded by our new world, data center operators need to look beyond traditional network and connectivity solutions. Cologix explains how a...