The Bathtub Curve and Data Center Equipment Reliability

May 11, 2020
Jake Blough, Chief Technology Officer for Service Express, explores the connection between the Bathtub Curve theory and data center equipment reliability and maintenance. 

Jake Blough, Chief Technology Officer for Service Express, explores the Bathtub Curve theory, its limitations,  and data center equipment reliability and maintenance. 

Jake Blough, Chief Technology Officer, Service Express

When digging into reliability engineering theories, you will quickly find the widely used Bathtub Curve. According to this theory, when a product is new to the market, there are substantial rates of early failures – which commonly result from an error with handling or installation. As the end of product life approaches, the rate increases due to a second and final wave of wear-out failures. Although the Bathtub Curve, pictured below, accurately reflects the failure behavior of many products, we have found it does not universally apply to data center equipment. 

Examining Reliability Data

At Service Express, we’ve collected over 15 years of equipment data from over half a million devices. The data tracks when equipment breaks, how it breaks and how often it breaks. The common assumption is that these devices should have a higher failure rate in their infancy and then again toward the end of life. However, in looking at non-critical and critical server and storage failures, our data shows that equipment failure rates do not follow the Bathtub Curve as expected.

Critical Server Failures

 A critical failure occurs when something like a CPU or system board fails. Critical server failures result in the loss of access to applications or data – impacting business productivity. In the graph below, you will see that most machines exhibit a failure rate between 0% and 0.2% with an outlier having an early production issue of 0.3%. These rates stay almost identical over a 10-15-year life span.

Non-Critical Server Failures

A non-critical failure occurs when a component like a disk drive or power supply fails. Modern data center equipment has built-in redundancy for these components, so no loss of data or access occurs in these instances. In the graph below, you will see a data set tracking non-critical server failure of several models over 13 years.

You can see that the non-critical failures barely increase over time with a failure rate of less than 0.5%; this is consistent with the number of components installed in the system. The more components in a system, the more chances of part vulnerability. The increase in failures toward the end of life seen here is attributed to the number of components in the system versus the wear-out factor associated with the Bathtub Curve. Systems in a blade form factor show much lower non-critical instances compared to large 4U 4-CPU form factor systems.

Critical & Non-Critical Storage Failures 

Storage devices are comprised of three types of components including critical, non-critical and disk drives. Critical parts typically include storage processors, whereas non-critical parts include cache batteries, power supplies and fans.

Storage systems are built to be incredibly resilient and tolerant of multiple failures before data is impacted. We consider storage processors to be the most critical components as a loss of a service processor will affect overall performance. In the graph above you can see critical, non-critical and drive failures for a popular OEM storage system. Note that over five years, critical storage failures occur between 0.1% and 0.2% – resulting in about one failure out of 1,000 systems per month. Non-critical faults are typically caused by cache battery sets which must be replaced every 3-5 years.

Disk Drive Failures

The graph above represents data for all disk drive failures over six years. You can see that disk drives experience a failure rate between 0.2% to 0.3%. Meaning that over time, disk drives are far more resilient than “common knowledge” would have you believe.

The long-term equipment reliability as illustrated by the data is a source of good news for IT departments. This failure data counters the traditional recommendation for a hardware refresh based on the expectation of increased failures as equipment ages. You can factor in longer equipment reliability and cost-savings when considering the timing of your refresh.

Your Next Data Center Refresh

 Of course, there are valid reasons for taking on the cost and time of a hardware refresh. Primary factors that should determine when a hardware upgrade is needed include:

  • Software compatibility
  • Hardware compatibility between devices
  • Performance capacity has been exceeded

If your equipment is meeting your immediate needs, consider delaying your refresh instead. Delaying an unneeded refresh can help you reduce your CapEx spend and improve the value of your original investment.

When it’s a question of spending tens of thousands of dollars on a refresh, you should evaluate your needs and access the facts to make the right decision for your environment. Based on our reliability data that shows stable failure rates over time for server and storage equipment, we recommend a refresh every 7-10 years. Your refresh cycle should always be driven by compatibility, capacity and reliability.

Jake Blough is the Chief Technology Officer for Service Express. 

About the Author

Voices of the Industry

Our Voice of the Industry feature showcases guest articles on thought leadership from sponsors of Data Center Frontier. For more information, see our Voices of the Industry description and guidelines.

Sponsored Recommendations

Guide to Environmental Sustainability Metrics for Data Centers

Unlock the power of Environmental, Social, and Governance (ESG) reporting in the data center industry with our comprehensive guide, proposing 28 key metrics across five categories...

The AI Disruption: Challenges and Guidance for Data Center Design

From large training clusters to small edge inference servers, AI is becoming a larger percentage of data center workloads. Learn more.

A better approach to boost data center capacity – Supply capacity agreements

Explore a transformative approach to data center capacity planning with insights on supply capacity agreements, addressing the impact of COVID-19, the AI race, and the evolving...

How Modernizing Aging Data Center Infrastructure Improves Sustainability

Explore the path to improved sustainability in data centers by modernizing aging infrastructure, uncovering challenges, three effective approaches, and specific examples outlined...

Julia Ardaran / Shutterstock.com

Beyond Hyperscale: Quantum Frederick's Vision for Sustainable Data Center Development

Scott Noteboom, CTO of Quantum Loophole, explains how Quantum Frederick created the first carbon neutral industrial zone.

White Papers

Download the full report.

2021 Overview of the Phoenix Data Center Market

April 6, 2021
This report, in conjunction with NTT, continues Data Center Frontier’s market coverage of growing data center hubs. Explore further for a comprehensive overview of the Phoenix...